Thursday, October 16, 2008

Wednesday, October 15, 2008

Wednesday, October 8, 2008

Ready to Pour Level 9

Monticello in the distance



Wednesday, October 1, 2008

Friday, September 19, 2008

Wednesday, August 27, 2008

A Level Going Up


Columns getting poured

Framing the deck

The laid out the deck

Post tension cables laid out for concrete

Friday, August 15, 2008

Tuesday, August 12, 2008

Friday, August 1, 2008

Thursday, July 24, 2008

Thursday, July 17, 2008

Coming Soon...


A Look at the Foundation

Below, you can see that the first three column lines are going in, along with the two exposed elevator pits. In addition to what is visible in the picture, work on the pile caps and grade beams continues.

Wednesday, July 16, 2008

The Foundation Going In

The below are photos of the concrete being poured for the foundation system that will support The Landmark.




It's Way Up There



Thursday, June 26, 2008

A Tower Crane Section Going Up

Mobilization - Sections

Sections of the crane are moving on site...

Mobilization

Mobilization of the tower crane is taking place this morning. With tight urban quarters it can be tricky at times, but it still stands as a testament to Century Concrete, Clancy & Theys, the City, the neighboring businesses, and the entire project team for such a feat.

Check back throughout the day for more images of the crane going up.



Tuesday, June 24, 2008

Tower Crane to Go Up June 26th and 27th

The tower crane will be going up June 26th & June 27th. Below are photos of the base being installed. The tower crane base is 20' x 20' and 4.5' thick of reinforced concrete.

All told, the tower crane will be over 160' high and visible from the miles away.


Friday, June 20, 2008

Productions Piles Complete!

With the drilling and placement of 139 auger cast piles, the site is now primed for the pile caps and grade beams. Before we can complete the foundation system, we have to install the tower crane.


Thursday, May 29, 2008